What is the easiest way to do this:
I have a group of tasks that I want to take 3 days. I have two resources
that I want to assign to those tasks. Now the actual task work won't take 3
complete days, I just want to block out that many days for the entire group.
So the resources may spend a couple hours on this task group, then have work
time left to assign to another task group, etc.
The only way I found to do this (and it may be the only way) is to set the
task duration to 0 days and go into the Resource Usage chart and put x-number
of hours on the task group for each resource. I have to divide up the number
of work hours between resources and spread them out across the 3 days. Is
there another way to do this?
I have a group of tasks that I want to take 3 days. I have two resources
that I want to assign to those tasks. Now the actual task work won't take 3
complete days, I just want to block out that many days for the entire group.
So the resources may spend a couple hours on this task group, then have work
time left to assign to another task group, etc.
The only way I found to do this (and it may be the only way) is to set the
task duration to 0 days and go into the Resource Usage chart and put x-number
of hours on the task group for each resource. I have to divide up the number
of work hours between resources and spread them out across the 3 days. Is
there another way to do this?