M
Mary
Is there a way to create a task and specify the work effort (in hours), then
duration, without it adjusting the work effort (i.e. increasing the hours) in
the Gantt view. Is there a default setting somewhere that sets this? (i.e.
I'm assuming I shoudl be able to create a task (from left to right in the
Gantt view, specifiying the work effort, then duration, then resources, and
project will take all the values I input and calculate the % for each
resource vs. adjusting the hours (work effort) to assume that 3 days = 24
hours.)
duration, without it adjusting the work effort (i.e. increasing the hours) in
the Gantt view. Is there a default setting somewhere that sets this? (i.e.
I'm assuming I shoudl be able to create a task (from left to right in the
Gantt view, specifiying the work effort, then duration, then resources, and
project will take all the values I input and calculate the % for each
resource vs. adjusting the hours (work effort) to assume that 3 days = 24
hours.)