F
Frank
I've done some searching but didn't find anything that spoke
specifically to what I'm trying to do.
I'm using Project 2003. My main question is related to equipment
delivery and the best way to deal with it. Here are the particulars:
1) We have ordered the equipment from the vendors, they have given us
delivery dates.
2) For some of the equipment the vendors are installing it, so the
dates on when they will be here are fixed.
3) For the equipment we are installing ourselves, work obviously can't
begin until the equipment arrives.
I've seperated the items into summary tasks, each with several sub
tasks (including delivery). An example is below:
Storage 12 days Wed 6/6/07 Thu 6/21/07
SAN Arrives 0 days Wed 6/6/07 Wed 6/6/07
SAN Implementation 4 days Mon 6/18/07 Thu 6/21/07
I've set the arrival task as a milestone. In this case both the
constrain dates are set to "Start no earlier than".
Is this the best way to approach this?
specifically to what I'm trying to do.
I'm using Project 2003. My main question is related to equipment
delivery and the best way to deal with it. Here are the particulars:
1) We have ordered the equipment from the vendors, they have given us
delivery dates.
2) For some of the equipment the vendors are installing it, so the
dates on when they will be here are fixed.
3) For the equipment we are installing ourselves, work obviously can't
begin until the equipment arrives.
I've seperated the items into summary tasks, each with several sub
tasks (including delivery). An example is below:
Storage 12 days Wed 6/6/07 Thu 6/21/07
SAN Arrives 0 days Wed 6/6/07 Wed 6/6/07
SAN Implementation 4 days Mon 6/18/07 Thu 6/21/07
I've set the arrival task as a milestone. In this case both the
constrain dates are set to "Start no earlier than".
Is this the best way to approach this?