Hi markaztec,
Well, it depends upon what you consider "Late". The formula below will
show the word "Late" if the finish of the task is scheduled to be later
than the baseline finish.
IIf([Finish]>[Baseline Finish], "Late", " ")
I hope this helps. Let us know how you get along.
Julie
Yeah been trying that, unfortunately I am very new to Microsoft Project
and
have no idea how to write the formula. I have tried many formulas to no
avail.
:
Hi,
You need to create a formula in Text1 (or any other text field) then
use
the
contents of Text1 as text for a new bar.
I suggest you create a new View to do this and edit the bar via Format,
Bar
Styles. Look for the text tab.
--
Rod Gill
Project MVP
Visit
www.msproject-systems.com for Project Companion Tools and more
I am trying to show the Activities that are late or on schedule on the
Gantt
Chart in Microsoft Project 2003. All I want is the word Late to
appear
next
to the activities that are late, but I want it to be automatically
calculated.