Duke
I am having a problem entering the actual work performed on a task. I need
to show the hours performed per day against the projected hours. For example
if a person was to work 4 hours on a line item but only worked 3 what is
happing to me is that the all the numbers for that resouce changes from 4 to
3. I need the baseline to stay at 4 and the actual to show 3.
to show the hours performed per day against the projected hours. For example
if a person was to work 4 hours on a line item but only worked 3 what is
happing to me is that the all the numbers for that resouce changes from 4 to
3. I need the baseline to stay at 4 and the actual to show 3.