Showing actual work in Project 03?

D

Duke

I am having a problem entering the actual work performed on a task. I need
to show the hours performed per day against the projected hours. For example
if a person was to work 4 hours on a line item but only worked 3 what is
happing to me is that the all the numbers for that resouce changes from 4 to
3. I need the baseline to stay at 4 and the actual to show 3.
 
J

JulieS

Hi Duke,

The Baseline Work should not be changing. I think what may be causing
the confusion is that if you look at the Resource Usage or Task Usage
view, it is not Baseline work which appears by default. It is work and
that work will change as you record actuals.

Make sure you save a baseline (Tool > Tracking > Save Baseline) before
you record actuals.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top