Snapshot 10-line maximum

R

Rachello

Does anyone know if there is any way around the 10-line maximum when taking a
snapshot of nonadjacent tasks in a gantt chart? Thanks!!
 
M

Mike Glen

Hi Rachello,

Welcome to this Microsoft Project newsgroup :)

Try using a Flag field to identify what you want and then filter for that
flag.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 