Hi Norma,
You're most welcome and sorry for the delay getting back to you. I
understand what you are trying to do much better now and I thank you for
the additional information. It appears from your description that you
are using a master project with inserted projects A, B, and C.
Unfortunately, as you have found there is no way to sort by the
Construction start dates, ignoring the Project summary task (Pipeline
Project A, Pipeline Project B). A somewhat convoluted workaround that
may work.
1) Apply the filter you have created to show only the Construction
tasks. That should show the data as you have described it in your first
list below.
2) Temporarily turn off the display of the Summary Tasks
(PipelineProject A, Pipeline Project B, etc.) by going to Tools >
Options, View tab and unchecking the "Show summary tasks" check box.
That should only show:
Construction - Start date 10/1/07
Construction - Start Date 8/16/07
Contruction - Start Date 8/15/07
3) Sort the listed tasks by Start Date giving you:
Contruction - Start Date 8/15/07
Construction - Start Date 8/16/07
Construction - Start date 10/1/07
4) Add a Text Field (Insert Column, select Text1) and in the text column
number the Construction tasks 1,2,3 in order of appearance.
Contruction - Start Date 8/15/07 - Text1 = 1
Construction - Start Date 8/16/07 - Text1 = 2
Construction - Start date 10/1/07 - Text1 = 3
5) Turn back on the display of the Summary tasks in Tools > Options.
This is going to add back the Project Summary tasks and will show the
tasks in their original order, but the Text1 field still shows the
numbers we added.
ID 1 - Pipeline Project A - Start Date 4/2/07
Construction - Start date 10/1/07 - Text1 = 3
ID 2 - Pipeline Project B - Start Date 4/9/07
Construction - Start Date 8/16/07 - Text1 = 2
ID 3 - Pipeline Project C - Start Date 4/9/07
Contruction - Start Date 8/15/07 - Text1 = 1
6) Copy the Text1 values to their summary tasks.
ID 1 - Pipeline Project A - Start Date 4/2/07 - Text1 = 3
Construction - Start date 10/1/07 - Text1 = 3
ID 2 - Pipeline Project B - Start Date 4/9/07 - Text1 = 2
Construction - Start Date 8/16/07 - Text1 = 2
ID 3 - Pipeline Project C - Start Date 4/9/07- Text1 = 1
Contruction - Start Date 8/15/07 - Text1 = 1
7) Sort by Text1 field. You can then hide the Text1 field.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project