A
asadim
Assume the following: You spend 3 hours on Task A and 4 hours on Task B today
(3/30/2007). How would you store these info in MSP 2007? This is something
like a timesheet (not a MSP timesheet; a real world company timesheet) in
which an employee stores his daily hours. As I understand MSP timesheets are
different than what I am refering to.
Now, in PWA there's My Tasks but it doesn't let you enter how many hours a
day you spent on Task A (instead it contains cumulative data -like 80% of
Task A is completed).
Perhaps I should ask my question this way: What is the standard way of
entering company timesheets in MSP?
(3/30/2007). How would you store these info in MSP 2007? This is something
like a timesheet (not a MSP timesheet; a real world company timesheet) in
which an employee stores his daily hours. As I understand MSP timesheets are
different than what I am refering to.
Now, in PWA there's My Tasks but it doesn't let you enter how many hours a
day you spent on Task A (instead it contains cumulative data -like 80% of
Task A is completed).
Perhaps I should ask my question this way: What is the standard way of
entering company timesheets in MSP?