D
DMM
Hi,
How do I setup a task so that it gets started on say 12/1/2005 and then the
resource goes and works on a different task on 12/2/2005. Finally, the
resource returns to the task on 12/3/2005. Is there a way to do this or
would I enter two separate tasks.
Thanks,
Devon
How do I setup a task so that it gets started on say 12/1/2005 and then the
resource goes and works on a different task on 12/2/2005. Finally, the
resource returns to the task on 12/3/2005. Is there a way to do this or
would I enter two separate tasks.
Thanks,
Devon