M
meljay
Hi,
I have previous asked the question re. taking a static 'snapshot' of a
master plan. This is so I can have a record of the progress of all the plans
without having to save 12 different plans.
It's been suggested that I remove the links (by double clicking each
inserted project, then unlinking in the Advanced Tab) and while this first
appeared to work I noticed the total % Complete changed dramatically (+15%).
Can someone please offer another suggestion and/or a reason why the % changed.
Thanks in advance
I have previous asked the question re. taking a static 'snapshot' of a
master plan. This is so I can have a record of the progress of all the plans
without having to save 12 different plans.
It's been suggested that I remove the links (by double clicking each
inserted project, then unlinking in the Advanced Tab) and while this first
appeared to work I noticed the total % Complete changed dramatically (+15%).
Can someone please offer another suggestion and/or a reason why the % changed.
Thanks in advance