J
Johnathan_
Hi,
I work with a series of seperate MS Project 2003 plans. There are several
team plans on which individual teams update their % complete progress and
start and finish dates. These plans are detailed and go up to ouline levels 5
and above.
There is also a "master" plan which shares the same outline level 5 tasks as
these team plans but does not concern itself with lower levels of detail.
What I need to do is take the % complete from each of the outline level 5
tasks in each of these team plans and copy them into the outline level 5
tasks in master plan.
Since there are so many team plans, I dont want to create an external links
between each of the team plans and the master plan (I know I can transfer %
complete this way) because there are hundreds of lines and it will break if a
task is deleted/changed.
I would like to write a macro for the master plan which takes the level 5
task for each team plan and transfers it to the master plan.
I think this is possible? How difficult would this be? I would really
appreciate if someone could suggest how I would go about this. I am quite
comfortable with VBA programming and can pick it up easily - I just need some
help to set me off. Otherwise can you suggest any alternatives to how I can
achieve this?
Many Thanks in advance,
Johnathan_
I work with a series of seperate MS Project 2003 plans. There are several
team plans on which individual teams update their % complete progress and
start and finish dates. These plans are detailed and go up to ouline levels 5
and above.
There is also a "master" plan which shares the same outline level 5 tasks as
these team plans but does not concern itself with lower levels of detail.
What I need to do is take the % complete from each of the outline level 5
tasks in each of these team plans and copy them into the outline level 5
tasks in master plan.
Since there are so many team plans, I dont want to create an external links
between each of the team plans and the master plan (I know I can transfer %
complete this way) because there are hundreds of lines and it will break if a
task is deleted/changed.
I would like to write a macro for the master plan which takes the level 5
task for each team plan and transfers it to the master plan.
I think this is possible? How difficult would this be? I would really
appreciate if someone could suggest how I would go about this. I am quite
comfortable with VBA programming and can pick it up easily - I just need some
help to set me off. Otherwise can you suggest any alternatives to how I can
achieve this?
Many Thanks in advance,
Johnathan_