Status date

P

Perl

Hello,

We have MSP 2003, I found out that status date
changed automatically. I can change it to n/a manually
but its happend very often.

Any idea ?

Pearl
 
J

Jim Aksel

Automatically? Not likely.
Check to see if someone else accessed the file and changed it.
I can also be done with a macro, even from another project file that
accesses this file.

I would think you would want to be changing that date regularly as you
status the schedule.
--
If this post was helpful, please consider rating it.

Jim

Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project
 