For those of you following this thread. The problem was calculation was
set to manual.
Visit
http://project.mvps.org/ for FAQs and more information about
Microsoft Project.
I'm sending it now. Thank you
:
Hi Nanc,
Okay, now I am confused. It doesn't take much
Why don't you zip the file and send it to me by email. I'll take a
look
and see if I can figure out what is going on.
My email address is:
passport 6847 at maine dot rr dot com
Remove spaces, replace at with @ and replace dot with .
I hope this helps. Let us know how you get along.
Julie
Visit
http://project.mvps.org/ for FAQs and more information about
Microsoft Project.
Yes the subtasks have been baselined. On the table the field for
finish
variance shows things like 5d and .5d and 3d, etc.
:
Hi Nanc,
I assume when you say the individual tasks come up with an error,
you
are saying that the formula creates an error.
If you add the Finish Variance field to the table, what is shown
in
the
finish variance for the subtasks? Have you baselined the
subtasks?
--
I hope this helps. Let us know how you get along.
Julie
Visit
http://project.mvps.org/ for FAQs and more information about
Microsoft Project.
This worked good on the summary tasks. They now have the
indicator
coming
out. But the individual tasks still come up with error.
Custom attributes I say formula
Calculation for task and summary rows None
If for task and summary rows I pick something other than none, I
get
ERROR
It is better, thank for that. Can you help at the detail task
row?
:
Hi Nanc,
Create the following formula in the Number1 field:
[Finish Variance]/480.
You need to divide the Finish Variance value by the number of
minutes
in
a day, so assuming your definition of a day is 8 hours, divide
by
480.
When you create the formula in the Customize Fields dialog box,
leave
the field to initially show you the data values to confirm that
the
formula is working correctly. The field should now show you the
number
of days late.
Then add the graphic indicator with your criteria:
Less than or equal to zero - color of your choice
Less than or equal to 10 - color of your choice
Greater than 10 - color of your choice.
--
I hope this helps. Let us know how you get along.
Julie
Visit
http://project.mvps.org/ for FAQs and more information
about
Microsoft Project.
Yes I'm looking at finish and baseline finish. I was trying
to
put
in
Number1 when the finish variance was greater than 14. But I
don't
know how
to do days. I want to know if things are ontime, up to 2
weeks
behind
to
finish, or more than 2 weeks to finish
:
Hi Nanc,
From your description, I assume you are trying to use a
comparison
of
[Finish] to [Baseline Finish]? If you have not saved a
baseline
that
could be the source of the error, but it is tough to tell
what
is
happening without some further information.
Please post what custom field you are using and your
formulas
and
we'll
see if we can help you sort it all out.
--
I hope this helps. Let us know how you get along.
Julie
Visit
http://project.mvps.org/ for FAQs and more information
about
Microsoft Project.
I've tried reading through the messages already on the
board,
but
I'm
sorry I
just don't understand what to do. I want a column on our
report
to
use the
graphical indicators of red,yellow,green for watching if
we
are
falling
behind.
I want to watch the tasks and if they are going to be 14
days
late
I
want
red, if they are between 0 and 14 days yellow, and if they
are
complete or on
track to finish on time I want green.
I've tried numerous formulas and alway have ERROR coming
up
in
the
field.