Hi, John
Thanks. Yes, I periodically highlight the whole column of tasks, go to the
task dialog/advanced, and set the task type to fixed duration. It seems to
work to change it for all the tasks. Nonetheless, MS project changes
durations and splits tasks.
The documentation says it will change duration if you have resource
calendars, etc., so I also tried to put all that on the same calendar. No joy.
Anyhow, I soled the problem by brute force: created a new file, adjusted the
standard calendar, and copied over one column at a time as text. It solved
all three problems. It now resource levels, does not split the tasks, and
does not change the task duration. So, something must have gotten corrupted
in the original file that I could not change.
Regards,
Larry