P
patcav33
i was wondering if it is possible to manually enter in red, yellow,
green status for an entire project, not the individual tasks. i have
seen instances where you can set a stoplight system up for individual
tasks based on finish variance if baselined, but what i want to do is
for the entire project overall, not the individual task. i want to
have it so that when you open up PWA (project server) and look at the
Projects in the Project Center summary view, you can see the red,
yellow or green stoplight status directly on that page is there a way
in project pro to set this up as a field to fill in and so that it
shows up in PWA? or can the red, yellow, green only come from
formulas set up for progress on tasks and the schedule overall.
any help or advice would be most appreciated
Pat C.
green status for an entire project, not the individual tasks. i have
seen instances where you can set a stoplight system up for individual
tasks based on finish variance if baselined, but what i want to do is
for the entire project overall, not the individual task. i want to
have it so that when you open up PWA (project server) and look at the
Projects in the Project Center summary view, you can see the red,
yellow or green stoplight status directly on that page is there a way
in project pro to set this up as a field to fill in and so that it
shows up in PWA? or can the red, yellow, green only come from
formulas set up for progress on tasks and the schedule overall.
any help or advice would be most appreciated
Pat C.