D
Dale Howard [MVP]
Tom --
Did you turn off the Estimated Duration options as I indicated in my last
post?
Did you turn off the Estimated Duration options as I indicated in my last
post?
"tshad" <[email protected]> said:I have a Summary Task that has no tasks under it. Just other Summary Tasks:
Project Summary "36 Days?"
Design "3.5 Days"
Development "18 Days"
Testing "10 Days"
Deployment "4.5 Days"
The Project Summary tasks is showing the Duration as "36 Days?" - what is
the "?" for? The duration total is correct.
Thanks,
Tom
Dale Howard said:Tom --
The question marks indicate an "Estimated" task. This indicates a task
whose Duration you did not manually enter, but which was calculated by the
software by entering Units and Work.
John said:Tom,
The question mark means that the duration is an estimate. Actually when
developing a plan, durations are always estimates, unless perhaps you
are counting the number of seconds in a minute.
To "turn off" the question mark, go to Tools/Options/Schedule tab and
uncheck the option to "show that tasks have estimated durations".
However the question mark automatically disappear from the duration when
subtask durations are no longer estimates (i.e. a discrete value has
been entered by the user or Project has calculated duration based on
work hours and resource assignments). The fact that your top level
summary line still has a question mark indicates that at least one
subtask or summary under it is still an estimate.
Tom,tshad said:You're right.
That was the problem. My last Summary task had a couple of tasks that I
hadn't added in the duration yet and that also had a question mark. Didn't
notice it until you mentioned it.
Thanks,
Tom
Dale Howard said:Tom --
Did you turn off the Estimated Duration options as I indicated in my last
post?
Want to reply to this thread or ask your own question?
You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.