C
Cheryl
Hello All,
I have my project files structured with an External
Dependencies section, activities sections, and a
deliverables section. The deliverables section of each
project file contains work products. The durations are
set to 0, however the summary task show duration times.
Example below:
External Dependencies 0 days 6/14/04
6/14/04
Task1 from ext proj file A 0 days 6/14/04 6/14/04
Task2 from ext proj file B 0 days 6/14/04 6/14/04
Activities 15 days 6/14/04 7/2/04
Define Schedule Structure 5 days 6/14/04 6/18/04 2
Manload Schedule 1 day 6/21/04 6/21/04 5
Create Test Plan 15 days 6/14/04 7/2/04
Deliverables 9 days 6/21/04 7/2/04
Manloaded Schedule 0 days 6/21/04 6/21/04 6
Test Plan 0 days 7/2/04 7/2/04 7
I have my project files structured with an External
Dependencies section, activities sections, and a
deliverables section. The deliverables section of each
project file contains work products. The durations are
set to 0, however the summary task show duration times.
Example below:
External Dependencies 0 days 6/14/04
6/14/04
Task1 from ext proj file A 0 days 6/14/04 6/14/04
Task2 from ext proj file B 0 days 6/14/04 6/14/04
Activities 15 days 6/14/04 7/2/04
Define Schedule Structure 5 days 6/14/04 6/18/04 2
Manload Schedule 1 day 6/21/04 6/21/04 5
Create Test Plan 15 days 6/14/04 7/2/04
Deliverables 9 days 6/21/04 7/2/04
Manloaded Schedule 0 days 6/21/04 6/21/04 6
Test Plan 0 days 7/2/04 7/2/04 7