summary task

M

mankoni

I have several tasks under each summary task.
The team can do the tasks under each summary task any order BUT give
me a estimate @ the summ task level. I do NOT want to enter duration or
track the the lowest level BUT need the lower level tasks captured for
clarity purposes.

Given the situation , can I just enter the duration and
dependencies for the summ task ? The duration for summ tasks are greyed
out in project.

Thanks
 
R

Rod Gill

Sorry, summary tasks summarise sub tasks, they don't push values down to
them so you can't enter summary durations etc.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top