Table Structure

P

Prav

Hi i just wondering when you put 100 hours between start and finish dates,
how the hours are being split in the Task Usage, and how can i see the table
structure for the 'Task Usage' Hours. Cheers
 
J

Jan De Messemaeker

Hi,

It would have been faster to try it... :)
Make your task fixed duration, enter duration, then assign a resoruce a,nd
enter work
Now look at the task usage.
You can use other contours or even enter a work contour as you like (i.e.
netering work quantities day by day).
Hope this helps,

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional