Task dependency across projects

R

rfarmer

How do you define a dependency between tasks, one of which is in project A and the other in Project B? Thank you.
 
J

John

R,
Use external links. They are like normal predecessors and successors
except the link is between different files and therefore the
predecessor/successor ID information includes the file path.

There are various ways to establish external links. Rather than try to
detail one or more here, check the Project help file. Just type
"external links" into the help answer wizard.

Hope this helps.
John
 