Task Duration Graphic

P

Philg

On the Gantt view the graphic shows the tasks shorter than expected although
it's correct in the duration column a dotted line similar to a split task
appears. I have seen this several times before and don't understandIs is this
a bug in MSP?
Phil
 
J

Jan De Messemaeker

Hi,

No. It is an inconsistency betwen your calendar options (Tools, Options,
Calendar) specifically the definition of what is a "day", and OTOH the
working time in a day (Tools, Change Working time
There's more in FAQ 5 (see URL of FAQs in my signature)
HTH
 