Hello MS project community,
I have a strange issue with a simple project network:
Task A 10 days duration, and task b 5 days duration with task A as
successor FS+0d. The issue happens when I increase task A duration, for
instance to 11 days: the gantt chart view for task b switches to a split task
view (dotted lines) and task b still starts on day 11. I was expecting when
increasing task A duration for Task b to start on day 12. On a fresh .mpp
file the behavior is the expected.
Is this a corrupted file?