G
GreenMonster
I have a tast that is going to take 371.5 total hours.
I have 5 resources set up to work from 8-5 monday - friday.
I have an additional resource set up to work 5:30 pm - 10:30 PM monday -
friday and also 7:00 am - 3:00 pm on saturday.
When assigining the 5 resources (8-5 Mon-Fri) to the task the duration
changes from 371.5 hrs to 77.81 hrs. Which is what I would expect.
However, when I add the sixth resource (5:30-10:30 Mon-Fri, 7:00-3:00 Sat)
the task duration increases to 128.67 hrs.
Why does the duration increase with the one additional resources assigned to
the taks rather then decrease? Won't the task take less time since the one
resources can work an additional 5 hours per day Mon-Fri and 7 hours on
Saturday?
I have 5 resources set up to work from 8-5 monday - friday.
I have an additional resource set up to work 5:30 pm - 10:30 PM monday -
friday and also 7:00 am - 3:00 pm on saturday.
When assigining the 5 resources (8-5 Mon-Fri) to the task the duration
changes from 371.5 hrs to 77.81 hrs. Which is what I would expect.
However, when I add the sixth resource (5:30-10:30 Mon-Fri, 7:00-3:00 Sat)
the task duration increases to 128.67 hrs.
Why does the duration increase with the one additional resources assigned to
the taks rather then decrease? Won't the task take less time since the one
resources can work an additional 5 hours per day Mon-Fri and 7 hours on
Saturday?