Hi All
After i link tasks with multiple project files, when ever i integrate them
into single project plan - because of ghost tasks i get mis links - meaning -
the link item i linked previsouly is getting changed (for ex: i have two
project plans - p1 and p2. when i link row 23 of p1 with row 40 of p2 - after
a integrated plan refresh i get row 41 of p2. how to avoid it - all i want
is, once linked the plan should not automatically change task link - is there
any option to switch off..??
Thanks.