M
Me
To start off, I am a novice Project user:
When using outlining to structure task lists, the indented subtasks are
tabbed approximatley six characters over. This used to be three characters.
On the surface this may not seem significant, but viewing and reporting
projects with a task hierarchy involving several levels of summary tasks, the
task column takes up a lot of screen or paper space, which limits the space
available for additional information.
Is there a way to change this setting?
This is the first time I have used Project since June, and as far as I know
I did not change any Project settings.
Edit: Microsoft Project 2000 9.0.2001.0219 SR-1
Thank you in advance.
When using outlining to structure task lists, the indented subtasks are
tabbed approximatley six characters over. This used to be three characters.
On the surface this may not seem significant, but viewing and reporting
projects with a task hierarchy involving several levels of summary tasks, the
task column takes up a lot of screen or paper space, which limits the space
available for additional information.
Is there a way to change this setting?
This is the first time I have used Project since June, and as far as I know
I did not change any Project settings.
Edit: Microsoft Project 2000 9.0.2001.0219 SR-1
Thank you in advance.