W
WillBuochs
I have a task that requires a machine and an operator to be completed.
Each is set up as a seperate resource with their own calendars. The working
time of the resources only overlap occaisonally (1 week in a month) based on
machine availability.
MS Project schedules the task to complete based on the availability of only
the operator (if "finish as soon as possible" constraint). It allocates all
the effort to the operator and none to the machine (or sometimes vica-versa).
It also sometimes splits the task.
How can I constrain the task to start when only both resources are available?
Each is set up as a seperate resource with their own calendars. The working
time of the resources only overlap occaisonally (1 week in a month) based on
machine availability.
MS Project schedules the task to complete based on the availability of only
the operator (if "finish as soon as possible" constraint). It allocates all
the effort to the operator and none to the machine (or sometimes vica-versa).
It also sometimes splits the task.
How can I constrain the task to start when only both resources are available?