Gavin Midgley
I have a descrepency of two days between the"Task Progress" bar and the
"Progress Line" when I update two particular tasks. Both tasks are showing
the same % complete in the "% Work Complete" and "% Complete" columns. Both
tasks are in excess of 500 hours duration with only 30 hours of work so the
manning levels are very low. Any solutions to the above would be greatly
appreciated.