Task Progress

T

Té

When I mark a task 25% using the tracking toolbar, and then I click the 50%
it continues to split the task. Why is this?
 
T

Té

Hi Mike! I found out the problem. I had the current date set to the wrong
date so that was why it was splitting it up! WHen I go to the task sheet in
tracking gantt view and enter 100% complete my remaining duration is in a
decimal format. Do you know why this could be?
 
M

Mike Glen

I'm not quite with you here. If it is 100% Complete there is no remaining
Duration. Try the reverse - enter Actual Work and Remaining work and let
Project calculate the % Complete.

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top