Task schedule vs actual time needed

H

Help me

Hello all

If I have a task that is going to start today and end in 3 weeks but only
needs 20 hours of actual work. How do I do this in project 2003 ?

Thank you
 
J

John

Help me said:
Hello all

If I have a task that is going to start today and end in 3 weeks but only
needs 20 hours of actual work. How do I do this in project 2003 ?

Thank you

Help me,
Simply enter the task Duration as 3 weeks (120 hr or 15 days). Then
enter 20 hr in the Work field. When a resource is assigned to the task
you will see that the resource is allocated at 17%.

Hope this helps.
John
Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top