T
Tom Friske
I have a project where I have several subtasks that are assigned a task type
of Fixed Work and one of the subtasks is assigned a task type of Fixed Units.
When I look at the summary task for these subtasks, the Baseline Work value
does not add up to the Baseline Work for all of the subtasks. If I change
the task type to Fixed Work for the one subtask that was assigned Fixed Units
and save the baseline (Tools -> Tracking -> Save Baseline and then "Select
Tasks" and "To all summary tasks"), the Baseline Work in the summary task now
adds up to the total in the Baseline Work column for all of the subtasks.
Am I correct in assuming that the Baseline Work value in a summary task will
not equal the sum of the Baseline Work for all of the subtasks if there is a
mixture of task types within a group of subtask? Could you explain to me why
this happens?
Thanks
Tom
of Fixed Work and one of the subtasks is assigned a task type of Fixed Units.
When I look at the summary task for these subtasks, the Baseline Work value
does not add up to the Baseline Work for all of the subtasks. If I change
the task type to Fixed Work for the one subtask that was assigned Fixed Units
and save the baseline (Tools -> Tracking -> Save Baseline and then "Select
Tasks" and "To all summary tasks"), the Baseline Work in the summary task now
adds up to the total in the Baseline Work column for all of the subtasks.
Am I correct in assuming that the Baseline Work value in a summary task will
not equal the sum of the Baseline Work for all of the subtasks if there is a
mixture of task types within a group of subtask? Could you explain to me why
this happens?
Thanks
Tom