E
EarlePearce
I feel stupid to ask this and I did read several messages but I don't see any
hope of a way to do what I MUST do.
I need to track actual man hours worked and manually enter their estimate of
percent complete for tasks, then have the Gannt bar extend to show a new
estimated duration.
Example: resource works 16hrs on an estimated 20h task but is only 50% done.
I need to see the 16hrs worked and the 50% complete and have Gannt extend
the estimated duration to 40h.
I know this runs counter to what I've read, but this is what I really must
do. Can I somehow get Project to do this via code or ? I'm now playing with
custom fields etc, and if somebody has done it I'd like their input.
hope of a way to do what I MUST do.
I need to track actual man hours worked and manually enter their estimate of
percent complete for tasks, then have the Gannt bar extend to show a new
estimated duration.
Example: resource works 16hrs on an estimated 20h task but is only 50% done.
I need to see the 16hrs worked and the 50% complete and have Gannt extend
the estimated duration to 40h.
I know this runs counter to what I've read, but this is what I really must
do. Can I somehow get Project to do this via code or ? I'm now playing with
custom fields etc, and if somebody has done it I'd like their input.