D
Darrell
When creating an assignment (task) I was trained to use the task type for the
variable that I do know and let the program calculate the variable that you
do not know. So, if I know the duration I use “Fixed Duration†and enter the
duration first. I then add either the estimated “work†or “units†based in
what I think I have, and then I allow MS Project to calculate the last
variable for me. I do this to DEVELOP my schedule. Once I have my schedule
developed and I set my baseline, I then change all of the task types to
“Fixed Units†to TRACK my progress because in general I do not want my
resource allocation (units) to change (since they have now accepted ownership
of the assignment) I want either my “duration†or “work†to change so that I
can track variance.
Can anyone provide an argument for TRACKING a schedule using something other
than “Fixed Units�
variable that I do know and let the program calculate the variable that you
do not know. So, if I know the duration I use “Fixed Duration†and enter the
duration first. I then add either the estimated “work†or “units†based in
what I think I have, and then I allow MS Project to calculate the last
variable for me. I do this to DEVELOP my schedule. Once I have my schedule
developed and I set my baseline, I then change all of the task types to
“Fixed Units†to TRACK my progress because in general I do not want my
resource allocation (units) to change (since they have now accepted ownership
of the assignment) I want either my “duration†or “work†to change so that I
can track variance.
Can anyone provide an argument for TRACKING a schedule using something other
than “Fixed Units�