Task Usage / % Complete representation

H

Hardip

Hi All,

Can anyone please advise on the best means to represent the following
scenario.

I have a resourced task scheduled to last 1 week, task type: duration, with
20 hrs assigned. The task finishes on time but consumes only 15 hours. The
% complete calculates this at 75% complete, where as in reality the task is
100% complete.

I've tried two different methods to update the % complete:

1) Manaually input this into the % Complete. However, when I input 100% the
actual work increases.
2) I've entered the actual work into the the task usage sheet. However, MS
Project recalculates the scheduled duration. Presumably, the applications
assumes the remaining work will be consumed at some point in the future.

Can anyone advise on the best method to handle this scenario? Can I
complete a tasks within fewer hours against that baselined and represent this
as 100%?

TIA - Hardip
 
R

Rod Gill

Hi,

In the Task Usage view set the remaining work to 0 which should restore your
duration. Or, in the Work column against the task set remaining work to 0.
This should set 100% complete with actual work still 15.
 
H

Hardip

Hi Rod,

Thanks for the reply. The task usage method doesn't seem to work but the
alternative approach appears to do the trick.

Thanks,
Hardip
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top