J
Jim Aksel
I am creating a new project in P2003SP3 using a 9/80 work calendar.
I have created a new calendar (9/80) with every other Friday off, along with
company holidays. The new calendar is assigned to the Project.mpp and
ResourcePool.mpp, and all resources in ResourcePool.mpp have a base calendar
assigned as 9/80.
Tools/Options/Calendar Tab is changed to reflect 9/80 work week in both
Project.mpp and ResourcePool.mpp. Default work hours set to 9 hours (7AM-5PM
with a 1 hour lunch), 17 days per month, 45 hours/week.
Resources from the pool seem to assign to Project.mpp nicely and show a
proper hours spread of 9 hours/day and every other Friday off.
In the Task Usage View, I am expecting every Saturday and Sunday to show
gray, and every other Friday show Gray.
The work spreads correctly to the 9/80 schedule along with days off.
However, all Fridays still appear yellow (available). The Resource Usage
view shows every other Friday as non-work day.
Am I missing something with the Yellow on every Friday or is Project.mpp
being stuborn? I would like to see the non-working Fridays as gray in the
Task Usage view.
I have created a new calendar (9/80) with every other Friday off, along with
company holidays. The new calendar is assigned to the Project.mpp and
ResourcePool.mpp, and all resources in ResourcePool.mpp have a base calendar
assigned as 9/80.
Tools/Options/Calendar Tab is changed to reflect 9/80 work week in both
Project.mpp and ResourcePool.mpp. Default work hours set to 9 hours (7AM-5PM
with a 1 hour lunch), 17 days per month, 45 hours/week.
Resources from the pool seem to assign to Project.mpp nicely and show a
proper hours spread of 9 hours/day and every other Friday off.
In the Task Usage View, I am expecting every Saturday and Sunday to show
gray, and every other Friday show Gray.
The work spreads correctly to the 9/80 schedule along with days off.
However, all Fridays still appear yellow (available). The Resource Usage
view shows every other Friday as non-work day.
Am I missing something with the Yellow on every Friday or is Project.mpp
being stuborn? I would like to see the non-working Fridays as gray in the
Task Usage view.