Hello,
At this moment I am trying to add new project data to the Project
database. I am doing this for Microsoft Project 2003. The Project
database contains several tables. One of them is the MSP_TASKS table.
This table hold a field called "TASK_CAL_UID" wich points to the
MSP_CALENDARS table. The default field value for "TASK_CAL_UID" seems
to be -1.
Now i have the following question. To wich field within the
MSP_CALENDARS table does the TASK_CAL_UID (MSP_TASKS) point (I guess
the "CAL_UID" or the "CAL_BASE_UID"?
And second, if the default value, -1, is specified, wich of the
available calendars is selected? I guess the default calendar will be
used. The one containing a "CAL_BASE_UID" = -1.
I hope someone can verify this for me. Thank you all in advance.
Gr,
Alex
At this moment I am trying to add new project data to the Project
database. I am doing this for Microsoft Project 2003. The Project
database contains several tables. One of them is the MSP_TASKS table.
This table hold a field called "TASK_CAL_UID" wich points to the
MSP_CALENDARS table. The default field value for "TASK_CAL_UID" seems
to be -1.
Now i have the following question. To wich field within the
MSP_CALENDARS table does the TASK_CAL_UID (MSP_TASKS) point (I guess
the "CAL_UID" or the "CAL_BASE_UID"?
And second, if the default value, -1, is specified, wich of the
available calendars is selected? I guess the default calendar will be
used. The one containing a "CAL_BASE_UID" = -1.
I hope someone can verify this for me. Thank you all in advance.
Gr,
Alex