Each time I attempt to create a task I get the
error: "Could not complete the operation. One or more
parameter values are not valid."

The due date: Fri 9/17/2004
The start date: Wed 9/17/2003
The reminder: Wed 9/17/2003 8:00 AM
 
C

Charles Beauregard [MSFT]

Go in your Tasks folder and choose Actions | Save Task
Order. If this menu item is disabled, you'll need to
clear anything in the "Filters" and "Group By" section of
the "Customize Current View..." dialog.

That should do it.