Hi, I have an summary task with a lot of milestones in it.
When I now like to write the name of the task to every
milestone, the texts are overlapping. Is it possible to
write the text vetically?
Thank you in advance
Michael
 
G

Gérard Ducouret

Hello Michael,

I guess that you used the "Roll up Gantt bar to summary" feature.
Sorry, it is not possible to write the text vetically, but you can write it
*over* the milestone symbol :
Format / Bar Styles...
get down to select the "Rollup Milestone symbol
Click the Text tab, Top : Name

Hope this helps,

Gérard Ducouret
 
J

John

Michael,
Unfortunately no. I suggest you use various combinations of text over,
under, on either side of the milestones. Use abbreviations to shorten
the text (use spare text fields instead of the Name field directly). You
also might try expanding the timescale to give more room.

Hope this helps.
John
 