S
Shannonevans
When I began tracking my project, some tasks where completed out o
order. I moved them to the correct time and reattached the links t
future work so it would reflect what was truely happening. I notice
when I put them 100% complete the duration changed. For some reaso
several of the tasked linked to that task changed the duration. I
seemed like they were ignoring the resource calendar when I put th
correct duration back in. Like working 5 ten hour day schedule, 3
hours should span over a three day period. It would show it as a littl
over 1 day, like it was on a 24 hr schedule. I also noticed that when
progressed the schedule the % complete changed on several tasks. Item
I put 50% complete went to 16%. What is up with that
order. I moved them to the correct time and reattached the links t
future work so it would reflect what was truely happening. I notice
when I put them 100% complete the duration changed. For some reaso
several of the tasked linked to that task changed the duration. I
seemed like they were ignoring the resource calendar when I put th
correct duration back in. Like working 5 ten hour day schedule, 3
hours should span over a three day period. It would show it as a littl
over 1 day, like it was on a 24 hr schedule. I also noticed that when
progressed the schedule the % complete changed on several tasks. Item
I put 50% complete went to 16%. What is up with that