Time from START

J

JoeM

I've been trying to search for this answer, but its hard enough for me to
explain, let alone search -sorry if its been touched before.

I want to build a simple gantt chart that shows 'days from start' or 'weeks
from start' rather than using absolute dates. Is this possible?

Heck, that wasn't so hard - that might even make sense????
 
D

Dale Howard [MVP]

JoeM --

Try this:

1. Open a project
2. Double-click the Timescale bar at the top of the Gantt Chart
3. Click the Middle Tiertab
4. Select "Weeks" as the Units and "Week1, Week2,....(from Start)" as the
Label
5. Click the Bottom Tier tab
6. Select "Days" as the Units and "Day1, Day2,...(from Start)" as the Label
7. Click the OK button

Hope this helps.
 
J

JoeM

Perfect!! That was exactly what I needed!


Dale Howard said:
JoeM --

Try this:

1. Open a project
2. Double-click the Timescale bar at the top of the Gantt Chart
3. Click the Middle Tiertab
4. Select "Weeks" as the Units and "Week1, Week2,....(from Start)" as the
Label
5. Click the Bottom Tier tab
6. Select "Days" as the Units and "Day1, Day2,...(from Start)" as the
Label
7. Click the OK button

Hope this helps.
 