greghoro
I have a strange circumstance with one of my projects.
In a Task Usage view, the Baseline Work does not roll up to the summary task
for time scaled data, it displays the information for the task immediately
below it.
The strange part is that in the table area of the same view, Baseline Work
rolls up to the project summary task. Also, other summary tasks in the time
scaled side roll up just fine, just not the project summary task.
I have cleared and re-baselined several times and have watched in the view
as the project summary task in the table area reflects the clearing and
re-baselining, albeit with incorrect numbers in the time scaled side.
And yes, I am using a level 0 project summary task as selected from the
Tools, Options, View menu. I have also performed a manual "Calculate Now"
although I don't believe it would have any effect.
No other projects behave this way, including an almost identical twin. They
all show Baseline Work rolling up to the project summary task.
Interestingly, it is not affecting Earned Value calculations for this
project, I would have thought it would affect BCWS, but it shows up correctly
in both the table and time scaled areas.
Any thoughts?
Greg
In a Task Usage view, the Baseline Work does not roll up to the summary task
for time scaled data, it displays the information for the task immediately
below it.
The strange part is that in the table area of the same view, Baseline Work
rolls up to the project summary task. Also, other summary tasks in the time
scaled side roll up just fine, just not the project summary task.
I have cleared and re-baselined several times and have watched in the view
as the project summary task in the table area reflects the clearing and
re-baselining, albeit with incorrect numbers in the time scaled side.
And yes, I am using a level 0 project summary task as selected from the
Tools, Options, View menu. I have also performed a manual "Calculate Now"
although I don't believe it would have any effect.
No other projects behave this way, including an almost identical twin. They
all show Baseline Work rolling up to the project summary task.
Interestingly, it is not affecting Earned Value calculations for this
project, I would have thought it would affect BCWS, but it shows up correctly
in both the table and time scaled areas.
Any thoughts?
Greg