Timescale in print dialog box greyed out -- why?

M

MTF

I'm using Project 2003 Pro. I'm trying to print a project summary report for
the month of August, but when I try to select the date range, it's greyed
out. Any idea how to change this?
 
J

JulieS

Hi MTF,

I don't believe it is possible to print a project summary report for
only a specific timespan -- the report is just that -- a summary of the
entire project.

You may be able to get close by creating a table applied to the Task
Sheet View to show the data from the Summary report (Start, Baseline
Start, Actual Start, Start Variance, etc.) and then applying filters to
show only the tasks in August. Then print the view.

I hope this helps. Let us know how you get along.

Julie

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top