Timescale on Gantt Chart shows wrong year

B

Benny

I have a project where all the entered dates etc are for 2007 yet the
timescale at the top of the Gantt chart shows the year as 2008.
The days and dates are correct for 2007 eg 30 July is shown for Monday
(correct for 2007).
Any ideas why this is happening?
thanks
Benny
 
B

Benny

Just found the answer.
I had the fiscal year set at July.
I changed it to January and it changed the year back to 2007.
 
M

Mike Glen

Hi Benny,

Welcome to this Microsoft Project newsgroup :)

Interestingly enough, that was the first FAQ written by us!
You might like to see FAQ Item: 1 on fiscal dates.
FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on :)

Mike Glen
Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top