Hi,

has anyone had a problem in Project 98 whereby when they select a timescale
in the print dialog box when printing a Gantt chart, all tasks are printed
anyway, regardless of late. Is there something that I am missing, or must a
filter be applied first. No service packs have been applied to Project 98,
though when looking a the list of fixes provided by the service pack it did
not seem to be in the list anyway.

Regards
 
J

Jan De Messemaeker

Hi,

Indeed, timescale selection is just a representtation thing, and does not
filter
There is a filter "Date range..." that can help you.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional