Randy:
You didn't provide enough information to give you a good answer. As Dale
told you, there's a big difference between publish and republish. If you're
using effort-based planning, and collecting hours by day, and only using
republish when actually required, then there's little likelihood that your
actions will move actual work displayed in the timesheet. However, if you
use republish on a task where actual work as moved as result of processing
in Project, you might move actual work around. It's a matter of a number of
factors including the task type in Project, and the tracking method settings
and how they interplay with one another and affect how time phased data is
calculated and written to the numerous tables in which actual work is
represented between Project and Project Server.
--
Gary L. Chefetz, MVP
"We wrote the books on Project Server"
http://www.msprojectexperts.com
-