Timesheet view in PWA

M

Maria

Can I modify timesheet view in Project web accesss? I´m using managed periods
and would like to non-working days eg. sundays and saturdays to be displayed
as different colour ( people can occasionally insert working time also for
weekend but I would like to visualise the non-working days better...)
 
D

Dale Howard [MVP]

Maria --

In the future, please post your Project Server questions in the
microsoft.public.project.server newsgroup, as this newsgroup is closing
down.

I'm not aware of any way to customize the Timesheet view as you wish. A
better approach is to do the following:

1. Log into PWA with administrator permissions
2. Click Admin - Customize Project Web Access
3. Set the "Number of weeks spanned" value to 1 week
4. Click the Save Changes button

Completing the above steps will add the day of the week to each date in the
column headers of the PWA timesheet page. Hope this helps.
 