D
Deb
My total cost is higher than the total of the task in the summary task as
well as the total cost. When I look at the cost in the cost views, their is
no evidence as to where the total comes from. The current example is the
project task total $135,964, but the project total shows $573,628. What's
wrong?
well as the total cost. When I look at the cost in the cost views, their is
no evidence as to where the total comes from. The current example is the
project task total $135,964, but the project total shows $573,628. What's
wrong?