V
Vicky
Hi,
I know this may sound not very logical, but I want to track the actual hours
without changing the start-finish date. I did set up the baseline project for
24 hour work days, but it still changes the date if the actual hours are more
than 24 hours.
I know it is doesn't make sense, but I was asked to do this and would love
to show them that this cannot be done in MS Project.
I know this may sound not very logical, but I want to track the actual hours
without changing the start-finish date. I did set up the baseline project for
24 hour work days, but it still changes the date if the actual hours are more
than 24 hours.
I know it is doesn't make sense, but I was asked to do this and would love
to show them that this cannot be done in MS Project.