M
Mike C
We are implementing EPM, which is based on Project 2003. We are looking to
account for all resources time in the system. There are many project that
are ongoing/utility projects which we need to track and book time to. The
problem is, in most cases we want to assign someone say 50% of their time to
it. This project would span the course of the year. So we want them
schedule 4 hrs per day everyday. If they book 5 hours today I do not want
project to respread the hours or adjust the duration. I want to de-couple
actuals from duration or total work. I have seen where you can de-coulpe %
complete, but not the others. Let me know your ideas.
Thanks
account for all resources time in the system. There are many project that
are ongoing/utility projects which we need to track and book time to. The
problem is, in most cases we want to assign someone say 50% of their time to
it. This project would span the course of the year. So we want them
schedule 4 hrs per day everyday. If they book 5 hours today I do not want
project to respread the hours or adjust the duration. I want to de-couple
actuals from duration or total work. I have seen where you can de-coulpe %
complete, but not the others. Let me know your ideas.
Thanks