K
Kesavan
Hi
I am using Project 2000.
Here is how my plan is organized.
Most of the tasks are "fixed work".
So I have hours allocated to each task and resources allocated
appropriately.
The plan is baselined.
Now when I entering the actuals, here is my problem -
When a task A completes in 12 hrs ( baselined at 16 hrs), I want to put
actual finish date and mark it 100% complete but with the actual hours = 12
hrs.
The tool automatically updates the actual hours to 16 but thats not true.
How do I track and report the actuals?
I am using Project 2000.
Here is how my plan is organized.
Most of the tasks are "fixed work".
So I have hours allocated to each task and resources allocated
appropriately.
The plan is baselined.
Now when I entering the actuals, here is my problem -
When a task A completes in 12 hrs ( baselined at 16 hrs), I want to put
actual finish date and mark it 100% complete but with the actual hours = 12
hrs.
The tool automatically updates the actual hours to 16 but thats not true.
How do I track and report the actuals?