I am trying to keep the base line intact while adding changes to the schedule
with out luck. I'm tracking individula changes via tool/tracking/update
tasks but when I add an actual start date it changes all my base line.
I assume that base line is the original information when project was created.
I'm new to MS Project. I'm I not inserting updates in the right place?